Resident Questions for Housing Area Panel

Reference Number: E.3.4

Department

Housing

Date question raised

13/10/2022

Week of Area Panel

12/12/2022 

Area in city

East 

Star rating applied by residents

Deadline for officer response

Wednesday 16th November 2022  

Name of officer responding

Adrian Day

Officer job title

Mechanical & Electrical Engineer

 

Resident Question

Title of Question

Maintenance Costs of incomplete aerial systems

Issue:

Residents are paying maintenance costs of aerial systems that were never fully commissioned.

Background:

Satellite aerials were rolled out and installed, but the system was never fully commissioned. Residents are paying the maintenance costs of this (Craven Vale, Robert Lodge).

Action requested by residents:

·         When are refunds going to be issued to residents for aerial systems that were never fully commissioned?

Officer Response

Officer contact details:

Adrian.Day@Brighton-Hove.gov.uk

 

Officer Response:

The aerial systems were installed in 2012, in 2021 these were upgraded to meet new requirements and regulations.

 

All aerial systems installed have been commissioned and are operating as expected and are maintained on a routine basis.

 

Should a resident experience issues with the aerial system this can be reported to repairs in the usual manner and a job will be raised and attended to by the specialist contractor appointed to the contract.

 

We are confident that systems are operating as expected, there is no consideration being given to provide a refund.

 

 

Action:

NONE

 

 

Start date:

16.11.2022

 

 

End date:

16.11.2022